Lyons Street (CR 77) at Sunrise River
Cities impacted : Linwood Township
Start Date: March 8, 2012
End Date: May 18, 2012 (Weather permitting)
What we are doing: This project will replace the bridge on Lyons Street over the Sunrise River. The new bridge will have shoulders, and the roadway leading up the bridge on either side will have shoulders.
How traffic is affected: During construction, Lyons Street will be closed to all traffic, and a detour will be in place Detour Map.
Additional Information:
Ad For Bid
Bid Abstract
20th Avenue (CSAH 54) at Hardwood Creek
Cities impacted : Lino Lakes
Start Date: April 23, 2012
End Date: May 25, 2012 (weather permitting)
What we are doing: This project will replace the box culvert style bridge on 20th Avenue over Hardwood Creek.
How traffic is affected: During construction, 20th Avenue will be closed to all traffic, and a detour will be in place Detour Map.